66-68 St Andrews Street, Hertford

ST ANDREW_EXPLODED AXO

Having been retained on the project by the new site owners, Leary Developments Ltd., work is underway on the working drawings for 66-68 St Andrew Street.

The surveyors have been on site to check the setting out and discussions are underway with the planners regarding some minor alterations to the permission. The client is planning a start on site in September this year.

We are developing the project as a BIM test case and are working closely with the Structural Engineers and Energy Consultants to develop a fully integrated 3d model of project. This can be tested and manipulated as the optimum construction methodology is developed.

Looking forward to seeing another project starting on site.


 

Forge Design’s ‘Open Studio’

 

FDS_04

We are looking forward to holding an ‘Open Studio’ event on Saturday 17th September.

Over the last three years we have been lucky enough to have worked on a great variety of projects including schemes for a number of our neighbours! The ‘Open Studio’ will be an opportunity for us to meet a wider cross-section of the local community, whilst inviting them into the office to see, and learn more about, what we do.

Further details will be released shortly. Watch local press for details

Please see our contact page for our address and other details.

IMG_1281


 

 

Gallery

Summer Garden Party

After a week of weather watch we welcomed a great number of our friends and colleagues to enjoy a glass of prosecco in the garden at The Forge on Friday 10th. We managed to dodge most of the showers however the new sail shades were called into action briefly and proved to be almost waterproof!

IMG_1214

The effort that everyone made to attend was much appreciated and it was a great chance to catch-up with progress within the office. The conversion of The Forge was much admired by those that hadn’t previously visited the office – it is hard to believe that, not only have been in the new space for more than a year, but we are coming up to our third birthday.

Time passes quickly when you enjoying yourself!!

This slideshow requires JavaScript.


 

Progress On Site…

Forge Design Studio has a number of projects currently under construction on site


Cedardore, West Wellow

IMG_3411

Setting-out and the below ground sub-structure has been completed at Cedardore for Mayflower Homes. The concrete beam and block floor is in and the first lift of masonary is well underway. Progress should be good as the better weather arrives!!

 


Cowesfield Lodge

IMG_3389

Site clearance and excavations have been dug and foundations poured at Cowesfield Lodge. The beam and block floor has been installed, and, as you can see, all the preparations have taken place ready for the mini-steel frame to arrive.  

Steel has been required to suit the light, open and airy extension. Almost 50sqm of new space is being created, as well the re-organisation of the existing house. This has been achieved under permitted development.

Richard Stanton at RFS is the Main Contractor.


North Brook End Stud

IMG_1178

The first phase of development is well underway at North Brook End Stud. The first floor staff apartment is being dry-lined, rooflights are in, the original exposed trusses have been cleaned. The contractors, Overton Builders, have got the first fix installations in place and are getting ready for the fit-out and all second fix joinery.


 

Gallery

BIM Training @ The Forge!

BIM TRAINING DAY 1

Forge Design Studio welcomed Jonathan Reeves into the office for two days of 3D Modelling/BIM training. Utilising our Vectorworks 2016 CAD package we fully explored the capabilities and potential of the system. The training is the first step towards our BIM Level 2 accreditation which we are currently undertaking.

Great progress was made and the opportunity to step outside of the day-to-day project work was welcomed by all.

We look forward to making full use of all the 3D modelling capabilities and, in particular, explored and verified the inter-relationship between our software and other industry standard systems.

IMG_3138

* nb Jonathan is the author of Innovative Vectorworks BIM, a recent publication which showcases many examples of BIM collaboration.


 

Redevelopment of Odyssey Health Club

Following lengthy negotiation with the Local Authority the application for the redevelopment of the Odyssey Health Club site has been resubmitted to the Planning Department. The overall design has retained its original quality whilst reducing the impact on the green belt through adjustments to the scale and massing of the proposals as well as the extent of the land take.

201415A_PL004

The apartments have been relocated to relate more closely to the existing Health Club buildings and a greater mix of units, including one and a half storey bungalows have been introduced in key locations.

The application is for 70 units together with the re-organisation of all the parking and approaches to the Health Club. The statutory consultation period is underway with a decision expected in Summer 2016.

A1 Illu MP


 

Portslade Regeneration

The practice is currently finalising the planning application for a comprehensive masterplan for the whole site including new build residential, conversion of the existing buildings and a community arts café/studio complex.

Details proposals have been developed which relate well to the surroundings within the context of the Conservation Area. Discussions have taken place with a number of existing Art Groups in Brighton to explore the nature of the spaces being created within the existing workshop building. Start-up artisan businesses will be encouraged.

Working closely with the Local Authority, public consultation has taken place and was very well attended. We look forward to making the final submission and the project moving forward to create a new chapter in the life of the Old Brewery.