Forge DS Project Updates!

Regeneration Projects

Regeneration of previously developed urban sites remains at the heart of many of our projects.

Major news for the year included the Former Brewery Site, Portslade which was granted Planning Consent in August. After an intensive period of work immediately preceding the Committee it was passed by an over-whelming majority. The proposal includes a mixed-use of 48 residential units, in a mixture of new build and conversion, together with a Creative Arts complex providing start-up, low rental employment space.

201503_PL017A

The proposals retained the conceptual principles that have been at the heart of the project from the outset with a careful blend of context and contemporary design. We are in continued discussion with our Client and look forward to the stage of the project.

Our first site in Hertford, the Former Waters Garage on North Road has continued on site whilst on the opposite side of the road!! …. construction work has started on 60-68 St Andrew Street. Both projects are complex insertions within close proximity to grade II Listed Buildings. The archaeological investigation which was required on 66-68 as part of the planning conditions was completed and a start on site was made in Summer. The hybrid construction of steel and masonry is well underway and the shape and form of the building is now evident.

On a different scale construction is nearing completion at North Brook End Stud on Dragonfly Barn. Marketing advice has been taken and the property will be brought to the Market early in the New Year – the impressive interiors and panoramic views have been very well received so far and we look forward to a successful sales process.

IMG_0646

IMG_0641


 

Progress On Site…

Forge Design Studio has a number of projects currently under construction on site


Cedardore, West Wellow

IMG_3411

Setting-out and the below ground sub-structure has been completed at Cedardore for Mayflower Homes. The concrete beam and block floor is in and the first lift of masonary is well underway. Progress should be good as the better weather arrives!!

 


Cowesfield Lodge

IMG_3389

Site clearance and excavations have been dug and foundations poured at Cowesfield Lodge. The beam and block floor has been installed, and, as you can see, all the preparations have taken place ready for the mini-steel frame to arrive.  

Steel has been required to suit the light, open and airy extension. Almost 50sqm of new space is being created, as well the re-organisation of the existing house. This has been achieved under permitted development.

Richard Stanton at RFS is the Main Contractor.


North Brook End Stud

IMG_1178

The first phase of development is well underway at North Brook End Stud. The first floor staff apartment is being dry-lined, rooflights are in, the original exposed trusses have been cleaned. The contractors, Overton Builders, have got the first fix installations in place and are getting ready for the fit-out and all second fix joinery.